Page 146 - DMGT206_PRODUCTION_AND_OPERATIONS_MANAGEMENT
P. 146

Unit 7: Efficiency and Effectiveness




                                                                                                Notes
                 Example: The “Pick up Trash” task must finish before the start of the “Mow Front” task
          in the Garden project.
          There are four kinds of task dependencies in Microsoft Project:
               Finish-to-start (FS)           Task (B) cannot start until task (A) finishes.
               Start-to-start (SS)            Task (B) cannot start until task (A) starts.

               Finish-to-finish (FF)          Task (B) cannot finish until task (A) finishes.
               Start-to-finish (SF)           Task (B) cannot finish until task (A) starts.
              You  can schedule  your tasks  most effectively  by entering  task durations,  creating
               dependencies  between tasks, and then letting Microsoft Project calculate  the start and
               finish dates for you.

              You can also specify lags between activities.
              As you keep on filling the information about the tasks, the Gantt chart is automatically
               created.

              You can track actual work using the time-phased fields in Microsoft Project.
              To keep your project on schedule, make sure that tasks start and finish on schedule.
              The Tracking Gantt view helps find trouble spots, tasks that vary from the baseline plan.
               You can then adjust task dependencies, reassign resources, or delete some tasks to meet
               your deadlines.
              The Tracking Gantt view pairs the current schedule with the original schedule for each
               task.
              When you’ve saved the project with a baseline, but before you’ve entered actual data on
               progress, the Tracking Gantt view shows tasks with the baseline bars and the scheduled or
               actual bars synchronized.
              When you update your schedule, you can compare the baseline plan to your actual progress
               to identify variances.
              You can click the Network Diagram button on the left on the main screen and the network
               diagram will be displayed.

              If you click on the Resource Sheet button given in the left column of the screen, the
               resource sheet  is  displayed. You  can fill in your  resource requirements.  It takes  the
               maximum number of units of a resource, by default, as unity (100%). It has a feature called
               Resource  Leveling.

              In the Gantt chart view, click on the Tools pull-down menu. Choose the Resource Leveling
               option.
              A dialog box appears, choose the Automatic radio button. There are three leveling options
               are given. Click on the Level Now button after choosing one or more leveling options and
               program reallocates resources, which can be seen both in the Gantt chart as well as the
               resource sheet.
              If you schedule tasks based on the availability of resources, track the progress of your
               tasks by updating the work completed on a task. Using this approach, you can track the
               work that each resource is performing.






                                           LOVELY PROFESSIONAL UNIVERSITY                                   141
   141   142   143   144   145   146   147   148   149   150   151