Page 115 - DMGT501_OPERATIONS_MANAGEMENT
P. 115
Unit 4: Process Selection and Facility Layout
Since just 0.098 hours are allowed to produce one unit, 5.56 stations must operate simultaneously, Notes
each contributing 0.098 hours, so that the required 0.356 hours are made available.
Theoretical minimum Number of stations = Time required/(unit time allowed/unit)
To produce 1 unit = 0.356 hours/(0.098 hours/unit) = 3.63 stations
Since only whole stations are possible, at least four stations are needed. The actual layout may
use more than the minimum number of stations, depending on the precedence requirements.
The initial layout in Table 4.3 uses nine stations.
The fourth step assigns tasks to each station. The designer must assign ten tasks to six or more
stations. Several assignment combinations are possible. In the example given earlier, TAMS
designed a system that provided a rectangular platen system manned by only five operators. All
assembly was completed on the platen with the sub-assemblies being transferred to a central
position on the platen for riveting.
For larger problems with thousands of tasks and hundreds of stations, we often use heuristics.
We will apply a Longest Operation Time (LOT) heuristic to find a balance for the 0.098 hours/
unit cycle time. The LOT steps are:
Heuristic Step 1: Longest operation time (LOT) gives the top priority of assignment to the task
requiring the longest operation time. Assign first the task that takes the most time to the first
station. However, the precedence requirements have to be maintained. In our example, task 'K'
requires the longest operation time of 5 minutes (the bottleneck operation); therefore, this task
has the highest priority of assignment at the first workstation. Table 4.4 shows that task 'K' has
precedence requirement of other tasks, i.e., there is a need for other tasks to be competed for the
execution of task 'K'. Therefore, task 'K' cannot be assigned to the first work-station. We have to
assign task 'A' as the first task.
Heuristic Step 2: In the first rule, task 'A' is the eligible task for the first workstation and is
assigned to it. As the task time of 'A' is 0.010 hours, and the bottleneck task is 0.098 hours,
additional tasks can be assigned to the station. Therefore tasks 'B', 'C', and 'D' which require a
total time of 0.080 hours can also be assigned to this station. The time available on station 1 after
completing these tasks is 0.008 hours. As there is no other task that has this timing, no more tasks
can be assigned to this station.
Heuristic Step 3: For workstation 3, we see that task 'H' requires the longest task time of 0.050
hours. From Table 4.4, notice that tasks 'I' and 'J' require 0.008 and 0.040 hours respectively. In
keeping with the precedence requirement, tasks H, I and J can be assigned to workstation 3 as the
total of the time required to complete these tasks is 0.098 hours.
Heuristic Step 4: Workstation 4 is the bottleneck station. The task 'K' cannot be split into parts,
this task has to be assigned to a workstation and the cycle time cannot be less than the duration
of this task. No other task can be accommodated at this workstation
Heuristic Steps 5-7: Repeat the above-explained process to get Table 4.4. Note that we have used
five workstations for the assignment of all the tasks. It could have been more; for example if task
'I' required more time, we would have ended up with 6 workstations. This explains why this is
called the theoretical minimum workstations.
This entire process, carried to completion, is summarized in Table 4.4, showing a five-station
assembly line comprising 10 tasks.
This layout is effective if it yields the desired capacity. It is efficient if it minimizes idle time.
Though the new assembly line design does increase the efficiency, as the idle time is significantly
reduced, it still does not yield the desired capacity. To be able to meet the demand of ABC
Electricals, in the example we have been following, we need to reduce the cycle time to 0.064
hours.
LOVELY PROFESSIONAL UNIVERSITY 109