Page 115 - DMGT521_PROJECT_MANAGEMENT
P. 115

Project Management




                    Notes              design calculations). It should also present a rough layout of various facilities and list out
                                       all the major equipments needed, with key specifications and available source(s) of supply.
                                       Moreover, it should  consider, and  evaluate, alternative  equipments as well and give
                                       reasoned recommendations about them. The importance of thoroughness of planning at
                                       this stage of the feasibility study can hardly be overemphasized. Many delays, cost overruns,
                                       and even failures of projects can be avoided provided the design and physical formulation
                                       of the project are based on a sufficiently deep analysis and have the support of the owner
                                       at the highest level. Otherwise, the project is likely to encounter midstream changes, with
                                       untoward consequences. There is a general impression that “minor” midstream changes
                                       would not pose much of a problem. This is not so. A project is a multi-task entity with
                                       complex linkages and interrelationships between its various constituents, and even “small”
                                       changes, which may result in certain made-to-order procured equipments being rendered
                                       unsuitable and thus throw the project schedule and costs haywire. The aim of all the efforts
                                       at this stage is to  design a viable operating  entity which  not only works, but  works
                                       harmoniously (and with minimum costs) in relation to the stipulated inputs and  local
                                       environment. Apparent as well as latent and relatively infrequent factors having a bearing
                                       on the effectiveness of the project must therefore be identified and considered. Neglect of
                                       climatic and geographical aspects (e.g. monsoons, floods, snowstorms, dust-storms, heat/
                                       cold-waves, earthquakes, typhoons, etc.) at this stage can prove quite costly later on. It is
                                       equally important to ascertain and give due consideration to local industrial and safety
                                       standards.
                                   6.  Construction Process: This needs to be tackled in. the feasibility study in terms of its five
                                       aspects, First, the methodology to be followed - viz., capital intensive or otherwise and its
                                       feasibility under prevailing conditions. Second, whether the construction or installation
                                       is to be done in-house, or on a turnkey basis, or by farming out a number of contracts for
                                       different work packages, and their feasibility. A  recommendation may also be  made
                                       whether any special agency(ies) should be engaged as a part of backup or contingency
                                       arrangements for critical  activity(ies). Third,  the determination  of such  construction
                                       equipments, materials and other essential inputs (like cement, sand, steel, stores etc.) as
                                       are to be arranged by the owner, along with their alternatives, availability, source of
                                       supply (local/foreign), lead-times, and infrastructural requirements (like uninterrupted
                                       supply of power, clean water, gas, steam, etc). Fourthly, the recommended sequence and
                                       time schedule of  different activities in the form of a bar  chart/PERT network. Lastly,
                                       assessment of the financial implications of this phase based on the latest available unit
                                       costs and with provision for inflation and contingencies.

                                   7.  Inputs: These relate to the operation phase of the project, but need to be identified at this
                                       stage of the feasibility study to examine the technical feasibility of the proposed system(s).
                                       For this, classification of the inputs into following categories will be found useful:
                                       (a)  raw materials,
                                       (b)  processed materials,
                                       (c)  components and subassemblies,

                                       (d)  spares and wear and tear parts,
                                       (e)  water and steam,
                                       (f)  gas, fuels and electricity.
                                       Next, their qualitative and quantitative  requirements (including  buffer stocks,  where
                                       applicable), availability, feasibility alternatives and reliable sources of supply should be
                                       carefully ascertained and record. The problems involved in their storage and handling
                                       should be also assessed.



          110                               LOVELY PROFESSIONAL UNIVERSITY
   110   111   112   113   114   115   116   117   118   119   120