             Case Study  Reliance Petro Jamnagar Refinery Ahead of Schedule










             For the June quarter Reliance Petroleum Ltd has overshot its  budget by   1,390  crore
             for setting up the Greenfield refinery at Jamnagar.
             The refinery project is expected to be completed ahead of the December deadline. It has
             achieved 94 per cent overall progress in implementing the project, the company said in a
             BSE statement.

                                                         159











             Reliance Petroleum is setting up the export oriented refinery, with a capacity to process
             580,000 barrels a day of crude. It is also setting up a 900,000 tonnes a year polypropylene
             plant.
             Reliance Petroleum in the statement said, "As on June 30, the company has utilised   25,515
             crore for the project against a projected utilisation of funds of   24,125 crore. The variation
             is mainly due to payments in advance under project contracts for continued efficient and
             speedy implementation of the project."
             The company added that the project engineering, procurement and contracting activities
             have been completed for the refinery.