                                     Case Study  HCL: When to do re-estimation?

                                     A       software company receives a web based development project from renowned
                                            client to develop vehicle tracking system for their organization.


                                     The software company is well set to start the project and preparing the ground work. They
                                     have done the sizing exercise based on the requirements shared by the client using Function
                                     Point methodology and arrived the size of 200 FP. It is JAVA based technology and by
                                     using their organization productivity of 0.8 FP/day (of high skilled resource), the efforts
                                     required to complete the development of the project is 250 Person days.
                                     Project manager started the project unfortunately he didn't get skilled resources. When
                                     the PM generates EV metrics for 1st week of the project, realized that the project is not
                                     going on track and there is 5% variance due to requirements delay from client.
                                     At the end of the 2 weeks PM found that variance is increased to 40%. The reasons added
                                     here are resources are not skilled enough to understand the requirements and prepare
                                     design documents.
                                     No of days estimated to complete the project = 250 Person Days
                                     No of Months to complete the project allocating 4 resources= 250/(20*4) = 3.125 PMs

                                     After 2 weeks, when the project manager generates the following metrics:






                                     The project is over budget and behind the schedule (please refer to appendix - A for details
                                     on metrics)
                                     PM  able to calculate above metrics as  he baselined the estimates and plan, compared
                                     actuals against baselined efforts.
                                     The remaining size of the application to be developed = 184 FP
                                     To complete 184 FP in 210 person days require = 184/210 = 1.14 against the 0.8 productivity
                                     assumed for initial estimation.
                                     Once the re-estimation done and baseline the Estimation, re-planning should follow and
                                     plan need to be baselined.

                                     Re-estimation at end of the project Phase
                                     An MNC awarded to develop employee leave details Portal
                                     Initially  project is  sized to  100  FP.  It is  JAVA based  technology  and by using  their
                                     organization productivity of 0.8 FP/day, the efforts required to complete the development
                                     of the project is 125 Person days.
                                     At the end of the Requirements phase the size of the project is increased by 50 FP due to
                                     scope creep.



                                                                                                         Contd...