Unit 2: The Project Life Cycle
Now the efforts required for 150 FP development, the efforts required are 187.5 person Notes
days. Re-planned based on the new estimates is required and adjust the efforts for the
remaining phases appropriately.
This needs to be repeated after each phase of the project till the end of the project.
Drawbacks if the re-estimation is not done and do not revise the estimation baseline
1. With the existing estimates and schedule, it is difficult to deliver the project for the
asked functionalities.
2. The quality of the work may effect if the timelines are not changed.
3. Credibility is lost at the client.
4. Getting skilled resources may be a challenge.
5. If more resources are added, the productivity may reduce as the communicate
channels increases and new resources may need time to understand application.
Question:
1. Analyse the case and discuss the case facts.
Source: http://www.ifpug.org/ISMA6/Kamana%20ISMA6.pdf