Unit 12: Critical Path Method and PERT




                                                                                                Notes
                Example: Draw a network for a house construction project. The sequence of activities with
          their predecessors are given in Table 12.1, below.
                       Table 12.1:  Sequence of  Activities for  House Construction  Project

               Name of     Starting and   Description of activity   Predecessor   Time duration
              the activity   finishing event                               (days)
                  A           (1,2)     Prepare the house plan   --          4
                  B           (2,3)     Construct the house     A            58
                  C           (3,4)     Fix the door/windows    B            2
                  D           (3,5)     Wiring the house        B            2
                  E           (4,6)     Paint the house         C            1
                  F           (5,6)     Polish the doors/       D            1
                                        windows

          Solution:

                   Figure  12.11:  Network  Diagram  Representing  House Construction  Project
                                                                 Polish the doors
                                      Fix the doors (2 days)        (1 day)
                                                            4     E
                   Prepare the    Construct the     C
                   house plan     house
                                                                          6
                      1            2           3
                            A           B
                          (4 days)           (58 days)  D           F
                                                            5     Paint the house
                                            Wiring the               (1 day)
                                            house (2 days)
          The network diagram in Figure 12.11 shows the procedure relationship between the activities.
          Activity A (preparation of house plan), has a start event 1 as well as an ending event 2. Activity
          B (Construction of house) begins at event 2 and ends at event 3. The activity B cannot start until
          activity A has been completed. Activities C and D cannot begin until activity B has been completed,
          but they can be performed simultaneously. Similarly, activities E and F can start only  after
          completion of activities C and D respectively. Both activities E and F finish at the end of event 6.


                 Example: Consider the project given in Table 12.2 and construct a network diagram.
                     Table 12.2:  Sequence of  Activities for  Building Construction  Project

               Activity               Description                   Predecessor
                  A      Purchase of Land                               -
                  B      Preparation of building plan                   -
                  C      Level or clean the land                        A
                  D      Register and get approval                     A, B
                  E      Construct the building                         C
                  F      Paint the building                             D