Page 244 - DCOM303_DMGT504_OPERATION_RESEARCH
P. 244

Unit 12: Critical Path Method and PERT




                                                                                                Notes
                                Table 12.3:  Activity Sequence  for a  Project
              Activity   A    B     C      D     E    F   G    H     I    J     K
             Predecessor   -   -     -     A     B    B   C    D    E    H, I   F, G

          Solution:
          The network diagram for the given problem is shown in Figure 12.14 with activities A, B and C
          starting simultaneously.

                                    Figure  12.14: Network  Diagram

                                         D                H         8
                                                   5
                                 2
                                                                           J
                       A
                                                             I
                                           E
                         B
                 1               3                      6                      9


                     C                             F
                                                                          K
                                 4
                                              G                  7






              Task   Draw a network diagram for a project given in Table.
              Activity   A   B    C    D    E     F    G    H    I    J    K     L
             Immediate   -   A    B    A    D   C, E   D    D    H    H    F, H   G, J
             Predecessor

          12.3 Critical Path Method (CPM)

          The  critical path  for any network is the longest  path through the entire network. Since  all
          activities must be completed to complete the entire project, the length of the critical path is also
          the shortest time allowable for completion of the project. Thus if the project is to be completed
          in that shortest time, all activities on the critical path must be started as soon as possible. These
          activities are called critical activities. If the project has to be completed ahead of the schedule,
          then the time required for at least one of the critical activity must be reduced. Further, any delay
          in completing the critical activities will increase the project duration.

          The activity,  which does not lie  on the  critical path, is called  non-critical activity.  These
          non-critical activities may have some slack time. The slack is the amount of time by which the
          start of an activity may be delayed without affecting the overall completion time of the project.
          But a critical activity has no slack. To reduce the overall project time, it would require more
          resources (at extra cost) to reduce the time taken by the critical activities to complete.






                                           LOVELY PROFESSIONAL UNIVERSITY                                   239
   239   240   241   242   243   244   245   246   247   248   249