Page 273 - DMGT206_PRODUCTION_AND_OPERATIONS_MANAGEMENT
P. 273

Production and Operations Management




                    Notes          In the example of ABC Electricals, TAMS looked at the bottleneck operation to see how it could
                                   be  improved. Initially  riveting (the  bottleneck operation) took place using a  5 tonne  press,
                                   which completed the riveting in two passes.  It had a rotating fixture that permitted riveting of
                                   two rivets simultaneously. The rotating fixture was removed and a die was designed so that
                                   riveting required just one pass. Testing took place immediately following riveting. Consecutive
                                   test failures were flagged up immediately allowing corrections to be made without a backlog of
                                   test failures. All acceptable products were then immediately laser marked with the company
                                   logo and specification. Finally, the product was unloaded to a multi-lane conveyor to packing.
                                   With the change in the bottleneck, the assembly line was redesigned using the LOT technique.
                                   As you can see, the newly designed assembly line had seven stations with 7 operators. This
                                   meant that there was an increase in the number of stations and workers. It was less efficient than
                                   the layout suggested earlier.
                                   However, though less efficient, the new system was able to reduce the cycle time 0.060 hours i.e.,
                                   the output had increased from 1960 units per month to 3200 units per month. This gave ABC
                                   Electricals the number of assembled Contact Breakers units they required. It also pruned the
                                   excessive costs so that ABC Electricals would eventually be more competitive.
                                   Very often, better results are obtained when the organization is effective rather than when it is
                                   efficient. Being more effective it reduced the costs of the product and ABC Electricals, the additional
                                   and unnecessary costs were not passed on to the customers. The form of the final assembly line
                                   is shown in Table 13.3.

                                                         Table  13.3: Final  Assembly Line  Design

                                             Preceding                                      Task    Operators
                                      Work                                   Predecessor
                                              Work         Task Assigned                  Time/Unit    per
                                     Station                                    Task
                                              Station                                      (Hours)    station
                                                                             None       0.010
                                                      A: Contact Breaker Assembly;
                                                                             A
                                                      Take Molding Half and clean
                                     1       -                                                      1
                                                      burrs etc.
                                                                             B          0.020
                                                      B: Install contacts
                                                                             A,C        0.020
                                                      C: Install Springs

                                                      D: Install plastic levers etc. on
                                     2       1                               A          0.040       1
                                                      Molding Half.
                                                      H: Close with other Molding   G   0.050
                                     3
                                             2        Half                                          1


                                                      I: Assemble 4 of the above   H    0.008
                                     4       3        units                                         1
                                                      J: Insert Rivets       I          0.040
                                     5       4        K: Rivet the sandwich units   J   0.060       1
                                     6       5        L: Switching Test under load   E   0.050      1
                                     7       6        M: Pack Contact Breaker unit   F   0.020      1
                                             Total                                      0. 354





          268                               LOVELY PROFESSIONAL UNIVERSITY
   268   269   270   271   272   273   274   275   276   277   278