                                                       Table 13.1:  Assembly Line  for Contact  Breaker

                                            Preceding                                       Task     Operators
                                     Work                                    Predecessor
                                              Work         Task Assigned                   Time/Unit    per
                                    Station    Station                          Task       (Hours)     station

                                                     A: Contact Breaker Assembly;
                                    1       -        Take Molding Half and clean   None    0.010         1
                                                     burrs etc.


                                                     B: Install contacts     A           0.020
                                                     C: Install Springs
                                    2       1                                B           0.020           2
                                                     D: Install plastic levers etc. on
                                                                             A,C         0.040
                                                     Molding Half.
                                                     E: Install contacts
                                                                             A           0.020
                                                     F: Install Springs
                                    3       1                                B           0.020           2
                                                     G: Install plastic levers etc., on
                                                     Molding Half.           A,C         0.040

                                                     H: Close with other Molding   G
                                    4       2,3                                          0.050           2
                                                     Half
                                                     I: Assemble 4 of the above   H      0.008
                                    5       4                                                            1
                                                     units
                                    6       5        J: Insert Rivets        I           0.040           1
                                    7       6        K: Rivet the sandwich units    J    0.098           1
                                    8       7        L: Switching Test under load    E   0.050           1
                                    9       8        M: Pack Contact Breaker unit    F   0.020           1
                                            Total                                        0. 354

                                   With a cycle time of 0.098 hours, how many contact breakers are produced daily? If the operation
                                   runs for one 8-hour shift each day, the available productive time each day is 8 hours. Therefore,
                                   maximum daily output can be as follows:
                                          Maximum daily output  = available time/(Cycle time/unit)
                                                               = 8.0/0.098 = 81.63 units

                                   Since  this assembly line can generate 81  units daily, and the requirement is  3000 units  per
                                   month, capacity is inadequate.

                                   An alternative method for determining whether capacity is adequate is to calculate the maximum
                                   allowable cycle time give a desired capacity 3000 units/month.

                                          Maximum allowable cycle time  = time available/desired number of units
                                                                       = (8 × 24)/3000 = 0.064 hours/unit
                                   This calculation shows that a layout whose cycle time is 0.064 hours or less will yield the desired
                                   capacity.
                                   Is the sequence of tasks feasible? For now, we will assume that the proposed sequence of tasks
                                   is feasible. By examining the product, we can see the sequence restrictions that must be observed
                                   in its assembly.