Page 270 - DMGT206_PRODUCTION_AND_OPERATIONS_MANAGEMENT
P. 270

Unit 13: Production Planning and Control




                                                                                                Notes
                 Example: The moldings have to be assembled prior to subsequent assembly steps to
          ensure that the four moldings can be connected together. Finally, the contact breaker cannot be
          assembled until the moldings have been riveted together.
          This sequence must be observed because the contact breaker cannot be assembled correctly in
          any other way. On the other hand, it makes no difference whether the contacts are placed before
          the plastic lever or after the springs are assembled in the molding. Similarly, the order of the
          riveting is irrelevant.
          In general, the  assembly tasks,  listed in the table, are broken down into  the smallest whole
          activity.  For  each  task,  we  note  in  column  4  of  Table  13.1, the  task  or  tasks that  must
          immediately precede it. However, job simplification is possible even within the requirement of
          precedence.
          Is the Line Efficient? The revised layout had six stations manned by 12 operators. All workers are
          paid for 8 hours daily. How much of their time was spent productively? This assignment to
          revise the layout was given to Technology and Management Systems (TAMS).
          ABC Electricals, due to the traditional approach, believed that the assembly was very labour
          intensive. Even with parallel processing they were utilizing up to twelve operators as is shown
          in column 6 of Table above.  TAMS decided to balance the assembly line.

          13.6.1 Assembly Line Balancing

          Given a capacity or production rate requirement, we can meet that requirement with a single
          line with a cycle time ‘c’, or with two parallel lines with a cycle time ‘2c’, and so forth. Line
          balancing programs have  been developed that enable the most efficient use  of the assembly
          line.

               !
             Caution In multiple parallel lines, as the number of parallel lines increases, so does the
             scope of job.
          We can also increase output by horizontal job enlargement, as has been demonstrated in the
          example of ABC Electricals. The point is that alternatives do exist.
          How can the cost of idle time of man and machine be reduced? Perhaps the ten tasks (A to M in
          Table above –  exclude tasks either at station 1 or station 2) can  be reassigned  so that more
          available employee time is used.
          An ideal assembly line would be one where tasks are assigned to different workstations in such
          a way that the total processing times at each workstation is equal. If every station used up an
          equal amount  of task  time, no  time would  be idle  time. Though  this  is  seldom  true,  an
          approximation of this condition can be achieved by effective assembly line balancing. The
          problem of equalizing stations is solved using six steps:

          1.   Define tasks.
          2.   Identify precedence requirements.
          3.   Calculate the minimum number of work stations required to produce desired output.
          4.   Apply an assignment heuristic to assign tasks to each station.
          5.   Evaluate effectiveness and efficiency.

          6.   Seek further improvement.



                                           LOVELY PROFESSIONAL UNIVERSITY                                   265
   265   266   267   268   269   270   271   272   273   274   275