Page 268 - DMGT206_PRODUCTION_AND_OPERATIONS_MANAGEMENT
P. 268

Unit 13: Production Planning and Control




          13.6 Defining the Layout Problem                                                      Notes

          The layout-planning problem for assembly lines, is to determine the minimum number  of
          stations (workers) and assign tasks to each station, so that a desired level of output is achieved.
          The design must consider the following aspects:

          1.   It should focus on achieving a desired level of output capacity.
          2.   The tasks assigned to stations and the sequence in which tasks must be carried out.

          3.   The output should be attained efficiently, without using minimum input resources.
          How this is achieved can be best understood with an example.


                 Example: ABC Electricals is a medium-sized firm in Delhi. It has an established design of
          a contact breaker assembly, used industry-wide to protect all electrical circuits. The company
          has established an assembly line to manufacture the product.
          The operator starts the assembly process with a molding half. Into this molding he puts the
          contacts, springs, plastic levers, etc. The assembly is closed off with a similar molding half. The
          final assembly, comprised up to four of these units, is secured with four rivets passing through
          the sandwich. The assembly is then tested. Testing is a critical operation, as the contact breaker
          assembly carries up to 415 volts. If the unit is found acceptable, it is labeled and packed for
          despatch.
          The method of assembly was on a series of benches with the sub-assemblies being placed in
          boxes for transfer to the riveting press. The rivet operation involved the manual placing of four
          long tubular rivets, pressing a 5 tonne press and securing the assembly. The product was again
          boxed for transfer to testing.
          The demand for this was 3000 units per month. However, due to the high rate of rejection and the
          highly labour intensive process, they were unable to meet the  demand. Table 13.1 gives  the
          assembly line details for the product.
          Is capacity adequate? The number of units this layout permits the company to produce each day
          depends on the station whose tasks take the longest time to perform. From the Table we know
          that:

          1.   The task assigned to station 1 requires 0.010 hours,
          2.   Station 2 and station 3 are parallel paths and the tasks assigned take 0.080 hours,

          3.   Station 4 requires 0.50 hours,
          4.   The longest time is needed at station 6 that is 0.098 hours, and so on.
          Since every unit passes through all stations, station 3 is the bottleneck operation. This station
          restricts the rate of flow of the line. With this layout, a finished contact breaker will flow to the
          end of the line every 0.098 hours. This time is called the cycle time of the line.
          The cycle time is, in fact, also the time after which the conveyor moves in a moving assembly
          line. Cycle time is defined as the time period after which completed units come off the assembly
          line. Completed units are available after each movement of the conveyor, as the basic structure
          worked upon at the last workstation will become a completed unit in that time.





                                           LOVELY PROFESSIONAL UNIVERSITY                                   263
   263   264   265   266   267   268   269   270   271   272   273