             Meeting Strict Deadlines                                                           Notes
             V-Guard  established  a  tight  six-month  timeframe  for  the  first  stage  of  its  SAP
             implementation. In response, IBM Global Business Services prepared  a plan  for a fast-
             track deployment based on the Ascendant SAP method.
             Subsequently, V-Guard worked with IBM to design and configure a comprehensive SAP
             solution that met the company’s requirements. The architecture is designed to enable V-
             Guard to expand the solution by adding new SAP application components as the need
             arises, based on a standardized, virtualized IT infrastructure.
             To meet the challenge of tight project deadlines, and to reduce the overall risk exposure
             during V-Guard’s sales season, IBM Global Business Services split the  implementation
             project into two phases. During the first phase, V-Guard worked with IBM to deploy SAP
             ERP 6.0 and modules for Sales and Distribution,  Materials Management, Production
             Planning,  Quality Management,  and Finance  and Controlling.  Additional  SAP  ERP
             modules, including Plant Maintenance and Human Capital Management, as well as SAP
             BusinessObjects™ Business Intelligence and SAP NetWeaver® Business Warehouse, were
             implemented over the course of two months during the second project phase.

             The IBM Global Business Services  team was confronted with a number of obstacles in
             bringing the business on board with the transformation effort. V-Guard’s legacy systems
             were strongly entrenched in the company’s operational culture, and moving from these
             systems and aligning  the business to standardized SAP processes without buy-in from
             most  users required a significant change management effort. It was also vital that the
             project conformed to complex statutory and legal requirements.
             IBM Global  Business Services  rose to these  challenges,  providing dedicated  project
             management and working closely with V-Guard to deliver the project a month ahead of
             schedule.

             “The  entire  implementation  was brilliantly  planned  and executed: we  kicked off  in
             September 2011 and the first project track went live in February 2012, beating our deadline
             by almost a month,” says Robin Joy. “There were no delays, and timelines were rigorously
             followed.”
             Based on the  excellent outcomes achieved with  the SAP  solution implementation, V-
             Guard has awarded IBM with a three year Application Maintenance Services contract. IBM
             Application Management Services will work closely with V-Guard to provide functional
             and technical expertise, and enable system and process improvements, helping the company
             to take its business to the next level.

             Harmonizing Business Processes
             V-Guard  has  successfully  completed  a  major  business  transformation  program,
             consolidating a disjointed system landscape on to a single, centralized SAP ERP platform.

             Important business processes have been integrated, creating a streamlined supply chain,
             stretching from procurement and inventory management to sales and distribution, product
             costing and financials. The company has cut complexity and introduced a high degree of
             business process automation. It is possible for V-Guard to track products at every stage
             from  materials  to  final  delivery,  ensuring  that  when  customers  demand  specific
             information, V-Guard can meet the need rapidly and easily.
             Improved Visibility at Every Level

             The  new solution provides V-Guard with much enhanced  visibility into  operations,
             offering a real-time view of  all its  manufacturing locations and distribution  centers.
                                                                                Contd....


                                           LOVELY PROFESSIONAL UNIVERSITY                                   203
   204   205   206   207   208   209   210   211   212   213   214