Unit 10: Simulation of a PERT Network (II)
Unit 10: Simulation of a PERT Network (II) Notes
CONTENTS
Objectives
Introduction
10.1 Critical Path Computation
10.2 Simulation of an Activity Network
10.3 Computer Program for Simulation
10.4 Summary
10.5 Keywords
10.6 Self Assessment
10.7 Review Questions
10.8 Further Readings
Objectives
After studying this unit, you will be able to:
Understand Critical Path Computation
Discuss the simulation of a activity network
Explain resource allocation and cost consideration
Introduction
CPM is commonly used with all forms of projects, including construction, aerospace and defense,
software development, research projects, product development, engineering, and plant
maintenance, among others. An activity network Diagram is also called: arrow diagram, network
diagram, activity chart, node diagram, CPM (Critical Path Method) chart or PERT (Program
Evaluation and Review Technique) chart.
10.1 Critical Path Computation
In the Activity Diagram described in the before, a network of tasks were set up to show the
dependent sequence of activities within a project. The Critical Path Method can be applied to
such as network to answer the most ordinary question asked of project managers: How long
will the overall project take?
Some ‘project management’ computer programs, such as Microsoft Project, will compute the
critical path for you. You can also do it by hand or build a spreadsheet to calculate it, using the
method described below.