Page 177 - DCAP601_SIMULATION_AND_MODELING
P. 177

Unit 10: Simulation of a PERT Network (II)



                                                                                                  Notes
                              Figure  10.2: Calculating  the  Early  Start  and  Finish





























            3.   Preliminary with the tasks at the end of the diagram, calculate the late start and late finish
                 for each task in turn, following the arrows in the reverse direction to the previous task, as
                 in the diagram below. The late finish is the same as the late start of the following task (for
                 the final tasks in the project, this is equal to the earliest completion date). If there is more
                 than one successor task, then there are several possible late figures. Select the smallest of
                 these. The late start for each task is the late finish minus the duration of the task. The final
                 calculation is for the earliest completion time for the project. This is calculated in the same
                 way as the early start date.
                               Figure  10.3: Calculating  the  Late  Start  and  Finish



























            4.   You now have, for each task, the initial and latest times that it can start and finish. Now
                 find the slack time (or ‘float’) for each task by subtracting the early start from the late start.





                                             LOVELY PROFESSIONAL UNIVERSITY                                  171
   172   173   174   175   176   177   178   179   180   181   182