Page 229 - DCOM202_COST_ACCOUNTING_I
P. 229

Unit 11: Contract Costing




               (d)   Sometimes  a  contract  is  nearing  completion,  say,  its  physical  progress  is  more   Notes
                    than 90% and the contractor is in a position to estimate the future costs with high
                    degree of accuracy. In such a case, it would the desirable to calculate the profit with
                    reference to total estimated profit. Total estimated profit is excess of contract price
                    over total estimated cost. The profit to be transferred to profit and loss account will
                    be calculated as under:
                        Profit = Estimated profit × (Work certified/Contract price)
                    If it is desired to transfer the realised profit to profit and loss account, it will be
                    calculated as under:
                        Profit = Estimated profit × (Work certified/Contract price) × (Cash received/
                               Work certified)
                    Where,
                        Estimated Profit = Contract price – Total estimated cost
                     Total Estimated Cost = Costs incurred upto date + Estimated costs for completion
                                       of contract.

                    [Important note: If nothing is given in the problem, students are advised to use the
                    concept of realised profit.]
          (xix)  Balance  Sheet:  At  the  time  of  preparation  of  balance  sheet,  the  contractee’s  account
               deserves a special mention. The contractee’s account is not to be shown as a debtor for the
               full contract price unless the work has been completed. Likewise the sum received from
               the contractee under various installments should not be shown as a liability on the balance
               sheet. On completion of contract, if the contractee still owes the amount to the contractor,
               his account is shown as a debtor for the amount due from him. When the contractee pays
               full amount, his account is closed and his account will not appear in the balance sheet.
          (xx)  Target Costing: This is a variation of cost-plus contract. Under target costing method, the
               contractee agrees to pay the profit as per the agreement or contract on the total contract
               price. In addition to the profit, some times, it is agreed upon by the contractor to complete
               the contract within a target price.
               In case, if he completes the contract within the target price, he is entitled to receive a bonus
               which  is  in  proportion  to  the  savings  made,  saving  being  difference  between  original
               contract price and target price.
          Compute a conservative estimate of profit on contract (which has been 90% complete) from the
          following particulars:

                                                                                     `
          Total expenditure to date                                            22,50,000
          Estimated further expenditure to complete the contract (including contingencies)   2,50,000
          Contract price                                                       32,50,000
          Work certified                                                       27,50,000

          Work uncertified                                                     1,75,000
          Cash received                                                        21,25,000
          Answer
          The contract is 90% complete, the method used for transfer of profit to Profit and Loss Account
          for the current year will be on the basis of estimated profit on completed contract basis.





                                           LOVELY PROFESSIONAL UNIVERSITY                                   223
   224   225   226   227   228   229   230   231   232   233   234