Unit 2: Managing Application Development Portfolio and Project Review & Selection




          responsibility of the committee is to take decision, which often requires more information than  Notes
          the proposal provides. It is, therefore, desired to have preliminary investigation to gather more
          details.  The steering committee approach is generally  favoured because  systems projects  are
          considered as business investments. Management, not systems analysts or designers, selects
          projects for development. Decisions are made on the basis of the cost of the project, its benefits
          to the organization and the feasibility of accomplishing the development within the limits of
          information systems technology.

          2.4.2 Information Systems Committee Method

          In some organization, the responsibility for reviewing project requests is entrusted to a committee
          of managers and analysts in the information systems department. Under this method, all requests
          for service and development are submitted directly to a review committee within the information
          systems department.  This committee approves or  disapproves projects  and sets  priorities,
          indicating which projects are most important and  should receive immediate attention. This
          method can be used when many requests are for routine services or maintenance of existing
          applications. When major equipment decisions are required or when long-term development
          commitments are  needed to undertake a project, the decision authority decided whether a
          project should proceed or not. So, the major functions of this committee are:
          (i)  To review the systems plan and approve/disapprove them.
          (ii)  To integrate the systems that share the input data.

          (iii)  To provide alternatives to the project.



              Task  Depict major functions of Information Systems Committee Method.

          2.4.3 User Group Committee Method


          In some organization, the responsibility for project decisions is entrusted to the users themselves.
          Individual departments hire their own analysts and designers who handle project selection and
          carry out development. Although the practice of having user committees for both choose and
          develop systems does take some of the burden from the systems development group it can have
          disadvantages for the users. Some users’ groups may find themselves with defective or poorly
          designed systems that require additional time and effort to undo any damage caused by the
          misinformation that such systems could generate.





             Notes   Although  users  groups  may  find  the  decisions  of  steering  committees  and
             Information Systems Committees disappointing at times, the success rate for users who
             undertake development job is not very encouraging.
          Project Request Contents


          The project proposals submitted by the users or the analysts to the Project Selection Committee
          is a critical element in launching the systems study. There is a general agreement that a project
          request form should contain the following:
              What is the problem?
              What are the details of the problem?